IRWIN & MACINTOSH LABS PROJECTS AT PAB BASEMENT LEVEL
Weekly construction update for the week of 9/2/14 9/5/14
This week's activities: 9/2/14 9/5/14
MEP Safe-off
Metal stud framed temporary barriers. (noisy work)
Plastic temp barrier at B03.
Drywall door infill at B03. (noisy work)
Demolition Demolition (noisy work)
Next week's activities:
Demolition and layout for our work. (noisy work)
Door and wall infill work at B03. (noisy work)
CONSTUCTION IMPACTS
Jobsite Working Hours: 6am to 3:30pm.
There will be temporary barricades in the hallways corridors a site logistics plan has been distributed
Questions: Please contact Sam Milroy at 650-280-0456 & sam@milroyinc.com or Marshall Wheel at 650-384-9281 & mwheel@stanford.edu