Fulton Street Transit Center Project: 3D/4D Model Application Report

TitleFulton Street Transit Center Project: 3D/4D Model Application Report
Publication TypeTechnical Report
AuthorsHartmann, T., W. Goodrich, M. Fischer, and D. Eberhard
NumberTR170
Date Published05/2007
Abstract

Within this report we describe the 3D/4D model implementation and application on the Fulton Street Transit Center (FSTC) project during July 2004 to July 2005. The Fulton Street Transit Center is one of the major subway reconstruction projects in New York City. With a budgeted project value of $750 Million the New York City Transit Authority (TA) plans to refurbish the seven subway lines around Fulton Street [Figure 1]. Furthermore, the TA plans to build a new above ground Transit Terminal. On this project a joint venture between Parsons Brinckerhoff and Bovis Lendlease formed the consultant construction management team to support the TA with the tasks of constructability review, bid packaging and site supervision.

Keywords3-D, 4-D, Case Study, Guidelines, VDC, Virtual Design and Construction
Year of Publication2007
AttachmentSize
TR170.pdf1.95 MB

Last modified Mon, 21 Mar, 2011 at 18:57