Stay up-to-date with the latest alerts about specific parking impacts in Escondido Village, and review past communications from our office about the Escondido Village Graduate Residences project.
EFFECTIVE DATE | ALERT |
Aug. 14, 2017 - Aug. 28, 2017 | Temporary partial closure of Quillen Court (6 spaces). |
July 17, 2017 - March 1, 2018 | Temporary partial closure of Comstock Circle Court (2 disabled parking spaces). [Map of Comstock partial closure] |
PUBLISHED | TYPE | SUBJECT |
Sept. 01, 2017 | Map | Sitewide Impacts. Updated Sept. 01, 2017 |
Sept. 01, 2017 | EVGR Car Free Club starts today! | |
Aug. 25, 2017 | Map | Sitewide Impacts. Updated Aug. 25, 2017 |
Aug. 24, 2017 | Alert | Permanent partial closure on Olmsted Road next to Hoskins Court (17 spaces) and between Quillen and the intersection of Campus Drive and Serra Street (11 spaces). [Map of Olmsted partial closures] |
Aug. 18, 2017 | Map | Sitewide Impacts, Update Aug. 18, 2017 |
Aug. 15, 2017 | Stanford Rewards for Being Car Free | |
Aug. 11, 2017 | Map | Sitewide Impacts, Updated Aug. 11, 2017 |
Aug. 10, 2017 | Transportation at Stanford: We can help | |
Aug. 4, 2017 | Map | Sitewide Impacts, Updated Aug. 4, 2017 |
July 31, 2017 | REMINDER: Cars parked in Thoburn Court parking lot will be towed Aug. 1 | |
July 28, 2017 | Map | Sitewide Impacts, Updated July 28, 2017 |
July 27, 2017 | Article | Thoburn Lot Closure on Aug. 1 (posted online and sent as a special eUpdate) |
July 24, 2017 | Map | Sitewide Impacts, Updated July 24, 2017 |
July 21, 2017 | What you need to know about transportation at Stanford | |
July 21, 2017 | Alert | UPDATED: Temporary partial closure on Olmsted Road (17 spaces). |
July 14, 2017 | Alert | OUT-OF-DATE: Temporary partial closure on Olmsted Road (10 spaces), effective July 20, 2017 - Aug. 20, 2017. [Map of Olmsted Road July - August closure] |
July 14, 2017 | Map | Sitewide Impacts, Updated July 14, 2017 |
July 12, 2017 | Article | Announcing the EVGR Car Free Club |
July 10, 2017 | Alert | UPDATED: Partial closure in Thoburn Court parking lot (6 spaces). |
July 7, 2017 | Map | Sitewide Impacts, Updated July 7, 2017 |
July 7, 2017 | Alert | OUT-OF-DATE: Partial closure in Thoburn Court parking lot (12 spaces), effective July 13. [Map of Thoburn partial closure] |
July 6, 2017 | Article | Construction Impacts on East Campus Continue as EVGR Project Progresses |
July 5, 2017 | Map | Zipcar Locations Near Escondido Village, Effective June 27 |
June 30, 2017 | Alert | Permanent partial closure in Quillen Court parking lot (6 spaces). |
June 30, 2017 | Alert | Permanent total closure of Thoburn Court parking lot. [Sitewide impacts map, updated June 30] |
June 30, 2017 | Map | Sitewide Impacts, Updated June 30, 2017 |
June 27, 2017 | Direct emails to 'ES'-permit holders parked in tow away zones as of 8 a.m. on Tuesday, June 27, 2017. McFarland Court, Jenkins Court, Hoskins Court | |
June 26, 2017 | REMINDER: Parking Closures Tomorrow, Tuesday, June 27 | |
June 23, 2017 | Map | Sitewide Impacts, Updated June 23, 2017 |
June 16, 2017 | Map | Sitewide Impacts, Updated June 16, 2017 |
June 16, 2017 | Alert | Relocation of two Zipcar locations in Escondido Village, effective June 27, 2017. [Map of Zipcar locations in Escondido Village] |
June 16, 2017 | Alert | Closure of five Marguerite bus stops along Olmsted Road, effective June 26, 2017. [Map of Marguerite bus stop closures] |
June 16, 2017 | Transportation updates for East Campus residents | |
June 12, 2017 | Alert | Temporary partial closure of Thoburn Court parking lot, effective June 14 - June 21, 2017. [Map of June 2017 Thoburn partial closure] |
June 12, 2017 | Parking options for ‘ES’-permit holders on East Campus | |
June 12, 2017 | Parking options for ‘C’-permit holders on East Campus (Corrected) | |
June 9, 2017 | Map | Sitewide Impacts, Updated June 9 |
June 8, 2017 | Alert | Temporary partial closure of Jenkins Court parking lot, effective June 15 - June 23, 2017. [Map of June 2017 Jenkins partial closure] |
June 6, 2017 | Article | East Campus Parking Lot Closures, Effective June 27 |
June 2, 2017 | Map | Sitewide Impacts, Updated June 2, 2017 |
June 2, 2017 | Alert | Intermittent temporary partial closures of Quillen and Hoskins Courts parking lots, effective May 30 - June 19, 2017. [Map of Quillen partial closures, Map of Hoskins partial closures] |
June 1, 2017 | East Campus Parking Lot Closures, Effective June 27 | |
May 24, 2017 | Map | |
May 24, 2017 | Alert | Permanent total closure of Jenkins, McFarland, and Hoskins Courts parking lots, effective June 27. [Map of Jenkins, McFarland, and Hoskins closures] |
May 24, 2017 | Timeline | Timeline of Escondido Village Parking Closures |
May 24, 2017 | Alert | Ten, 20-minute loading zones will be established in Escondido Village for 'ES'-permit holders, effective June 20, 2017. [Map of Escondido Village loading zones] |
May 24, 2017 | Permanent Parking Lot Closures, Effective June 27 | |
May 19, 2017 | Map | |
May 12, 2017 | Map | Sitewide Impacts, Updated May 12, 2017 |
May 4, 2017 | Alert | Permanent partial closure of Quillen and McFarland Court parking lots, effective May 17. [Map of Quillen and McFarland closures] |
May 1, 2017 | Alert | Temporary partial closure of Jenkins Court parking lot (23 parking spaces) and McFarland Court parking lot (7 parking spaces), effective May 5 - May 19, 2017. [Map of Jenkins and McFarland closures] |
April 28, 2017 | Alert | Permanent total closure of Blackwelder Court parking lot, effective May 21. [Map of Blackwelder total closure] |
April 24, 2017 | Alert | Temporary partial closure in Quillen Court parking lot (6 parking spaces), effective May 4 - May 9, 2017. [Map of Quillen temporary closure] |
April 24, 2017 | Alert | Temporary partial closure of Jenkins Court parking lot, effective April 24 - May 1, 2017. |
April 21, 2017 | Alert | Temporary partial closure in Quillen Court parking lot (16 parking spaces), effective May 1 - May 3, 2017. [Map of Quillen temporary closure] |
April 20, 2017 | Parking Impacts in Escondido Village Could Affect 'C'-Permit Holders | |
April 20, 2017 | Upcoming Parking Closures to Impact 'ES' Permit Holders | |
April 20, 2017 | Alert | Temporary total closure of Blackwelder Court parking lot, effective April 20-28. [Map of Blackwelder temporary closure] |
April 17, 2017 | Alert | Temporary partial closure in Quillen Court parking lot (8 parking spaces), effective April 24. |
April 17, 2017 | Alert | Permanent partial closure in Jenkins Court parking lot (2 parking spaces), effective April 24. |
April 17, 2017 | Alert | Temporary partial closure in Thoburn Court parking lot (11 parking spaces), effective April 21, 2017. [Map of Thoburn Court closure] |
April 17, 2017 | Alert | Temporary partial closure in Jenkins Court (7 parking spaces), effective April 19 - April 20, 2017. [Map of Jenkins Court closure] |
April 14, 2017 | Alert | Twenty-six parking spaces will be unavailable in Blackwelder and Jenkins Courts to make space for tree removals at various times April 17 through April 21. |
April 7, 2017 | Alert | Tree removals associated with the Escondido Village Graduate Residences Project will prompt partial closures of Quillen Court and Jenkins Court parking lots on April 11, and similar closures of Hoskins Court and Thoburn Court parking lots on April 12. [Map of EVGR April Parking Impacts] |
April 7, 2017 | Alert | Various areas of the parking lot in Blackwelder Court will be impacted April 7 - April 21 by tree removals and underground utility work associated with the Escondido Village Graduate Residences project. [Map of EVGR April Parking Impacts] |
March 28, 2017 | Alert | The sidewalk between the Blackwelder Court parking lot and Escondido Road will be periodically closed throughout the month of April 2017. [Map of sidewalk closures] |
March 22, 2017 | Alert | The entire McFarland Court parking lot will be closed April 4 and 5 (Tuesday and Wednesday) for tree removals associated with the EVGR project. [Map] |
March 6, 2017 | Alert | Twenty-nine parking spaces on the west end of Blackwelder Court will be permanently closed, effective April 3, 2017. [Map of Blackwelder Court partial closure] |
March 6, 2017 | Alert | Bike racks near Blackwelder, Studio 2, McFarland, and Hoskins will be affected by construction in Escondido Village. Bikes parked in these areas should be moved before March 1. For more information, see Project Management's Feb. 17 construction update. |
Feb. 28, 2017 | Article | Board of Trustees Approves Revised Parking for Escondido Village |
Feb. 27, 2017 | FAQ entry |
Will parking close all at once when the construction project starts? Not all parking will close at once. The lots will be closed in a phased approach over several weeks and months. You can find alerts about parking impacts as they unfold on our "Alerts and Archive of EVGR Communications" page. P&TS and EV residents will be able to assess parking impacts and make adjustments as needed. Please be assured that P&TS will monitor parking utilization and will address concerns to the extent possible. Contact us at transportation@stanford.edu if you have concerns or suggestions. |
Feb. 15, 2017 | Alert | Plans for the Escondido Village housing project set to move forward in late spring. For more information, view the latest Stanford News article. |
Feb. 1, 2017 | Alert | Underground utility work will affect parking in the Blackwelder Ct. lot and require the temporary relocation of Zipcar parking spaces within the lot. |
Jan. 18, 2017 | Alert | Utility work will affect parking near Hoskins Ct., McFarland Ct., Jenkins Ct., and Blackwelder Ct. Jan. 18 - Jan. 31, 2017 |
Jan. 2017 | Article | Escondido Village January Parking Update |
Jan. 2017 | Web page | How is P&TS is Responding to EV Residents' Concerns and Requests? |
2016 |
FAQ entry |
Will households be able to purchase or extend EV parking permits? Since construction is scheduled to begin during Winter Quarter, EV residents are allowed to purchase more than one permit per household through Jan. 8, 2017. Those with ES permits will continue to have access to parking in EV parking lots until construction begins. Prior to construction beginning, notices will be sent and posted and will include alternative parking options. |
2016 |
FAQ entry |
Why was the notice posted saying that parking would go away as of Oct. 15, 2016? Oct. 15, 2016, was the earliest date we were given when construction might begin and parking could be eliminated. As in this case, construction projects sometimes have an estimated start date but are delayed. Rather than wait to communicate the anticipated parking changes when there may be little time for residents to plan and adjust, we communicated the expected changes based on the earliest potential date we were given. Our intention was that residents would then be able to anticipate and plan for the change well in advance |
Nov. 28, 2016 | Web page | Escondido Village Parking Update (11/28/16) |
Nov. 16, 2016 | Article | Update Regarding Escondido Village Parking During Construction |
Nov. 8, 2016 | Article | Parking Changes Within Escondido Village Construction Areas |
Oct. 12, 2016 | Article | Anticipate Parking Impacts During Construction of Escondido Village Graduate Residences |
August 2016 | Article | Parking Changes Within Escondido Village Construction Areas |
Aug. 22, 2016 | Article | Update on EV Parking During Construction Starting This Fall |