Providing students with quality housing is a central goal of Residential & Dining Enterprises. Throughout the summer, several upgrades are being made to housing facilities on campus to increase building safety, update mechanical systems and enhance student comfort. Refer to the map below for the location of facilities affected by this work.
 

 

Building Renewal Projects 2015

Map of Renewal Projects

Click each house to see the site logistics plan.

KairosPhi Kappa Psi

Buildings Affected

Kairos

586 Mayfield Avenue

Phi Kappa Psi

592 Mayfield Avenue

Construction Timeline

June 16 - September 1, 2015

Construction Updates

September 18, 2015

Summer work on both Kairos and Phi Kappa Psi Row Houses is now complete.

We thank you for your patience throughout construction!

Completed exterior at Kairos

Completed exterior at Kairos

Completed exterior at Kairos

Completed exterior at Kairos

Completed exterior at Kairos

Completed exterior at Kairos

Completed exterior at Kairos

Completed interior at Kairos

Completed interior at Kairos

Completed interior at Kairos

Completed interior at Kairos

Completed interior at Kairos

Completed interior at Kairos

Completed interior at Kairos

Completed interior at Kairos

Completed exterior at Phi Kappa Psi

Completed exterior at Phi Kappa Psi

Completed exterior at Phi Kappa Psi

Completed exterior at Phi Kappa Psi

Completed exterior at Phi Kappa Psi

Completed exterior at Phi Kappa Psi

Completed exterior at Phi Kappa Psi

Completed exterior at Phi Kappa Psi

Completed exterior at Phi Kappa Psi

Completed exterior at Phi Kappa Psi

Completed exterior at Phi Kappa Psi

Completed exterior at Phi Kappa Psi

Completed interior at Phi Kappa Psi

Completed interior at Phi Kappa Psi

Completed interior at Phi Kappa Psi

Completed interior at Phi Kappa Psi

Completed interior at Phi Kappa Psi

Completed interior at Phi Kappa Psi

 

 

Work Completed

  • Site demolition
  • Structural, electrical, and plumbing upgrades
  • New enclosed stairwells
  • Student room, bathroom, and laundry refresh
  • Wood floor repairs
  • Carpeting replacement as needed by the renovation work
  • Exterior stucco repairs and replacement
  • Roof repairs and replacement
  • Window repairs and replacement
  • New decks, walkways, and landscaping

 

Contact Information

  • For any issues found in either Row House as the move-in process takes place, please call the Construction Hotline at (650) 725-5031. The information line is monitored Monday - Friday during regular business hours of 8am - 5pm.
  • If your call is of an urgent matter and requires immediate assistance, please call the Maintenance Hotline at (650) 725-1602 or email HousingRenewal@Stanford.edu.. Every effort will be made to respond to your inquiry promptly.